SUMMARIZED GENERAL INFORMATION ON THE IMPLEMENTATION OF THE PROGRAM MEASURES IN TERMS OF DIRECTIONS, PROBLEMS AND EXPECTED STRATEGIC RESULTS

ESR: 2.6.1.3. The automated system for accounting and monitoring the consumption and quality of fuel procured for the needs of the Armed Forces has been created

Progress in the implementation of measures as of 03.07.2024
measures, the implementation of which as of 31.03.2024
1 2 2 2
7
Partially implemented In progress Not implemented Not started
Measures implemented (fully and partially) - 1 ( 14.3%)
Name of the ESR Name of the measure The main implementer Monitoring results (latest) Status % of measures implemented (fully and partially) Evaluation of achievement of ESR Середній рівень ОСР
Direction 2.6. Defense sector
14.3% 1 / 7
0.0%
Problem 2.6.1. Nontransparent and ineffective usage and disposition of defense land, immovable properties in the defense industry, as well as surplus movable property of the army, intellectual property; uncontrolled consumption of fuel procured for the needs of the Armed Forces
14.3% 1 / 7
0.0%
3.1 ОСР 2.6.1.3. The automated system for accounting and monitoring the consumption and quality of fuel procured for the needs of the Armed Forces has been created 2.6.1.3.1 Drafting an order of the Ministry of Defense on the automated system for accounting and monitoring the consumption and quality of fuel, defining the key parameters of the system contributing to effective accounting and management of fuel and lubricants: 1) specialized intrusion-proof software that logs and stores each system login and identifies the user logging in, along with the relevant hardware and communications needed to organize automated data exchange within the system; 2) automated accounting and monitoring system in tank farms with the use of ultrasonic level meters; 3) online monitoring of tanks with fuel and lubricants focusing on the following indicators: product level in the tank, product temperature, product density, and percentage of bottom water; 4) a fuel tanker truck route GPS monitoring system. Ministry of Defenсe of Ukraine The measure was implemented on time, but partially Partially implemented
14.3% 1 / 7
0.0%
3.2 2.6.1.3.2 Holding a public discussion of the draft order indicated in subclause 2.6.1.3.1, and ensuring its revision (if needed), issuance, and submission for state registration Ministry of Defenсe of Ukraine The measure has not been implemented Not implemented
3.3 2.6.1.3.3 Supporting the state registration of the order indicated in subclause 2.6.1.3.1 and its official publication Ministry of Defenсe of Ukraine The measure has not been implemented Not implemented
3.4 2.6.1.3.4 Preparing a statement of work (“technical assignment”) for the automated system for accounting and monitoring the consumption and quality of fuel at all organizational units of state enterprise (if they receive deliveries of fuel and lubricants) and military units under centralized management of the Ministry of Defense Ministry of Defenсe of Ukraine There is progress in the implementation of the measure In progress
3.5 2.6.1.3.5 Arranging the development of software for the automated system for accounting and monitoring the consumption and quality of fuel at all organizational units of state enterprise (if they receive deliveries of fuel and lubricants) and military units under centralized management of the Ministry of Defense Ministry of Defenсe of Ukraine Implementation of the measure has not started Not started
3.6 2.6.1.3.6 Ensuring the pilot launch of the automated system indicated in subclause 2.6.1.3.5 Ministry of Defenсe of Ukraine There is progress in the implementation of the measure In progress
3.7 2.6.1.3.7 Ensuring the commercial launch of the automated system indicated in subclause 2.6.1.3.5 Ministry of Defenсe of Ukraine Implementation of the measure has not started Not started