Progress in the implementation of measures as of 21.11.2024
measures, the implementation of which as of 30.09.2024
1 1 1 1 1
5
Implemented Partially implemented In progress Not implemented Not started
Measures implemented (fully and partially) - 2 ( 40%)
Display in tabular form

Measures — 5

2.5.10.3.1. Developing and signing documentation for the implementation of the tool for digital management of the rebuilding (modernization) of Ukraine, which will ensure public access to an interactive map of projects, including those involving the rebuilding (modernization) of Ukraine, with information about competitive bidding processes completed, contracts signed, contractors and current progress of construction all over Ukraine, making it possible to monitor the progress of renovations and construction and avoid overlapping operations at the same sites

The main implementer: Ministry for Communities and Territories Development of Ukraine

2.5.10.3.2. Conducting pilot operation of the digital management tool indicated in subclause 2.5.10.3.1, adjusting it (if needed), and putting it into commercial operation.

The main implementer: Ministry for Communities and Territories Development of Ukraine

2.5.10.3.3. Ensuring constant operation (with public access) and updating of the interactive map of projects, particularly projects to rebuild (modernize) Ukraine, with information about competitive bidding processes completed, contracts signed, contractors and current progress of construction all over Ukraine, making it possible to monitor the progress of repairs and construction

The main implementer: Ministry for Communities and Territories Development of Ukraine

2.5.10.3.4. Developing technical documentation for integration of the interactive map of projects, including projects to rebuild (modernize) Ukraine, with the Unified State Electronic System in Construction

The main implementer: Ministry for Communities and Territories Development of Ukraine

2.5.10.3.5. Conducting pilot operation and performing the commercial launch of the interactive map of projects, including projects to rebuild (modernize) Ukraine, integrated with the Unified State Electronic System in Construction

The main implementer: State Agency for Restoration and Infrastructure Development of Ukraine

Indicators — 3

Evaluation of achievement of ESR — indicator weight —
1
0 / 40%

The tool for digital management of the rebuilding (modernization) of Ukraine has been implemented, which will ensure public access to an interactive map of projects, including those involving the rebuilding (modernization) of Ukraine, with information about competitive bidding processes completed, contracts signed, contractors and current progress of construction all over Ukraine, making it possible to monitor the progress of renovations and construction and avoid overlapping operations at the same sites.

i
2
0 / 30%

The interactive map of projects is functioning, including projects to rebuild (modernize) Ukraine, which openly displays up-to-date information on contracts, contractors, and the current progress of construction throughout the country.

i
3
0 / 30%

The interactive map of projects, including projects to rebuild (modernize) Ukraine, has been integrated with the Unified State Electronic System in Construction.

i
* - certain measures are common to several ESRs, but have a separate number (id)