SUMMARIZED GENERAL INFORMATION ON THE IMPLEMENTATION OF THE PROGRAM MEASURES IN TERMS OF DIRECTIONS, PROBLEMS AND EXPECTED STRATEGIC RESULTS
Problem: 2.4.2. Insufficient transparency of privatization procedures and failure by buyers to comply with the terms of the sale of the privatized asset
Progress in the implementation of measures as of
05.03.2026
5 |
50%
2 |
20%
3 |
30%
10
ImplementedPartially implementedNot implemented
Measures implemented (fully and partially) -
7 (70%)
№
Name of the ESR
Name of the measure
The main implementer
Monitoring results (latest)
Status
% of measures implemented (fully and partially)
Direction 2.4.
Public and private sectors of the economy
70%
7 /
10
Problem 2.4.2.
Insufficient transparency of privatization procedures and failure by buyers to comply with the terms of the sale of the privatized asset
70%
7 /
10
1.1
ОСР
2.4.2.1.
Instruments have been put in place to prevent the negative impact of privatization authorities and organizers of privatization auctions on the number of bidders and competition.
ОСР
2.4.2.2.
The most common problems encountered in the performance by buyers of the mandatory conditions of the sale and/or operation of a privatized asset have been assessed; the findings of this assessment have been factored into the practices of privatization authorities
The measure was implemented on time, but partially
Partially implemented
3.1
ОСР
2.4.2.3.
Small-scale privatization or lease of state and municipal property is carried out using the electronic system Prozorro.Sale and in compliance with the principles of fair competition