Feedback from the public

Measure

2.2.2.4.2 (2). Digitizing information about natural resources (geological data, information about aquatic and forest resources) and available irrigation systems, hydraulic structures, and pump stations

Measure status:

Implemented

Actual execution date:

31.03.2024

The measure is aimed at achieving ESR:

2.2.2.4. An information and analytical system for management of natural resources management has been introduced, which provides open access to up-to-date information on natural resources, contains the functionality of electronic services, electronic reporting, traceability, environmental monitoring and inspection, as well as an open software interface for creating analytical and visual (geoinformation) software based on the data of this information and analytical system (without the right to modify such data)

Problem solving:

2.2.2. Arbitrary application of mandatory rules for businesses, which is accompanied by attendant corruption risks

Deadlines:

01.03.2023 - 29.02.2024

Responsible implementors (authorities):

The main implementer: Ministry of Agrarian Policy and Food of Ukraine
co-implementors:
State Agency of Ukraine for the Development of Melioration, Fisheries and Food Programs

Sources of funding:

state budget

Volumes of financing (thousand UAH):

within the established budget allocations for the relevant year

Performance indicator:

Information about natural resources has been digitized.

Implementing status

Progress/Result of implementation:

According to the Ministry of Agrarian Policy, information on existing irrigation systems, hydro-technical structures, and pumping stations transferred by the State Water Resources Agency has been digitized. Software for public use is under development.

Taking into account the information provided, the measure can be considered implemented in the part within the remit of the Ministry of Agrarian Policy.

Monitoring results (quarterly):

14.05.2024:
The measure was implemented on time and in full
13.02.2024:
There is no progress in the implementation of the measure
15.11.2023:
There is no progress in the implementation of the measure
14.08.2023:
Implementation of the measure has started on time

Key sources of assessment:

Additional sources of information: