Direction 2.5.
Construction, land relations, and infrastructure
10.3%
3 /
29
0.0%
Problem 2.5.10.
Imperfection of existing control instruments and lack of transparency of road construction, repair, and maintenance processes
10.3%
3 /
29
0.0%
1.1 (1)
ОСР
2.5.10.1.
With regard to public infrastructure projects, the mandatory publication of all information required by the Law of Ukraine On the Openness of Spending of Public Funds and data disclosure in accordance with
CoST IDS (Infrastructure Data Standard) and publication of data (including design documentation and methodology for calculating the anticipated cost of procurement) in a machine-readable format in accordance with OC4IDS and OCDS standards
2.5.10.1.1 (1) Arranging the publication of the entire array of data defined in Part 1 of Article 3 of the Law of Ukraine On the Openness of Spending of Public Fund on road infrastructure projects on the Unified Web Portal on the Spending of Public Funds, particularly with respect to:
1) the administrator (recipient) of budget funds (name, identification code of the legal entity, address, last name, first name and patronymic of the manager);
2) the chief administrator of budget funds (name, address, last name, first name and patronymic of the manager);
3) the amount of budget allocations and/or budget subsidies for the relevant budget periods — total amount and broken down by budgetary programs;
4) the amount of budget expenditures and loans extended from the budget during the reporting period — total amount and broken down by budgetary programs (this must also include a listing of the kinds and amounts of the relevant revenue streams with respect to funds of the special fund of the budget);
5) information about contracts concluded during the reporting period (the subject matter of the contract, the contractor (name, identification code of legal entity, place of business address), the contract price, the unit price (if any), the quantity of goods, work and/or services purchased, whether or not the procurement process was held and, if not, the grounds for skipping the procurement process with a reference to the law, the amount of payments made under the contract during the reporting period, and the effective term of the contract);
6) information about the status of performance of contracts signed in previous reporting periods, with all appendices forming an integral part of such contracts (the subject matter of the contract, the contractor (name, identification code of legal entity, place of business address, last name, first name and patronymic of the manager), the contract price, the unit price (if any), whether or not the procurement process was held and, if not, the grounds for skipping the procurement process with a reference to the law, the amount of payments made under the contract during the reporting period, whether or not there have been any claims or penalties arising out of the performance of the contract, certificates of delivery and acceptance (certificates of services rendered, certificates of delivery and acceptance, performance of work), if any);
7) the number of business trips, including the number of business trips abroad, the total amount spent on business trips, including the amount spent on business trips abroad.
State Agency for Restoration and Infrastructure Development of Ukraine
The measure was implemented on time and in full
Implemented
10.3%
3 /
29
0.0%
1.1 (2)
2.5.10.1.1 (2) Arranging the publication of the entire array of data defined in Part 1 of Article 3 of the Law of Ukraine On the Openness of Spending of Public Fund on road infrastructure projects on the Unified Web Portal on the Spending of Public Funds, particularly with respect to:
1) the administrator (recipient) of budget funds (name, identification code of the legal entity, address, last name, first name and patronymic of the manager);
2) the chief administrator of budget funds (name, address, last name, first name and patronymic of the manager);
3) the amount of budget allocations and/or budget subsidies for the relevant budget periods — total amount and broken down by budgetary programs;
4) the amount of budget expenditures and loans extended from the budget during the reporting period — total amount and broken down by budgetary programs (this must also include a listing of the kinds and amounts of the relevant revenue streams with respect to funds of the special fund of the budget);
5) information about contracts concluded during the reporting period (the subject matter of the contract, the contractor (name, identification code of legal entity, place of business address), the contract price, the unit price (if any), the quantity of goods, work and/or services purchased, whether or not the procurement process was held and, if not, the grounds for skipping the procurement process with a reference to the law, the amount of payments made under the contract during the reporting period, and the effective term of the contract);
6) information about the status of performance of contracts signed in previous reporting periods, with all appendices forming an integral part of such contracts (the subject matter of the contract, the contractor (name, identification code of legal entity, place of business address, last name, first name and patronymic of the manager), the contract price, the unit price (if any), whether or not the procurement process was held and, if not, the grounds for skipping the procurement process with a reference to the law, the amount of payments made under the contract during the reporting period, whether or not there have been any claims or penalties arising out of the performance of the contract, certificates of delivery and acceptance (certificates of services rendered, certificates of delivery and acceptance, performance of work), if any);
7) the number of business trips, including the number of business trips abroad, the total amount spent on business trips, including the amount spent on business trips abroad.
Ministry for Communities and Territories Development of Ukraine
The measure was implemented on time and in full
Implemented
1.2
2.5.10.1.2 Development of State Agency for Reconstruction and Development of Infrastructure of Ukraine order regulating the issue on publication of open data in accordance with an appendix to Regulation on sets of data to be published as open data, approved by Regulation of Cabinet of Ministers of Ukraine as of October 21, 2015, no.835, that are due to be made public as State Agency for Reconstruction and Development of Infrastructure of Ukraine data;
State Agency for Reconstruction and Development of Infrastructure of Ukraine full implementation of requirements of Cabinet of Ministers of Ukraine as of October 21, 2015 no.835 and the order; ensure publication of open data on Unified state open data web portal in accordance to the set of data related to the CoST IDS standard (Infrastructure Data Standard), publication of data (such as project documentation and expected procurement cost calculation methods) in machine-reading format in acc. to OC4IDS and OCDS standards
State Agency for Restoration and Infrastructure Development of Ukraine
The measure was implemented on time, but partially
Partially implemented
1.3 (26)
2.5.10.1.3 (26) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Khmelnytskyi regional state administration
Implementation of the measure has not started
Not started
1.3 (1)
2.5.10.1.3 (1) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
State Agency for Restoration and Infrastructure Development of Ukraine
There is progress in the implementation of the measure
In progress
1.3 (25)
2.5.10.1.3 (25) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Kyiv City State Administration
Implementation of the measure has not started
Not started
1.3 (24)
2.5.10.1.3 (24) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Chernihiv Regional State Administration
There is progress in the implementation of the measure
In progress
1.3 (23)
2.5.10.1.3 (23) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Chernivtsi regional state administration
There is progress in the implementation of the measure
In progress
1.3 (22)
2.5.10.1.3 (22) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Cherkasy regional state administration
Implementation of the measure has not started
Not started
1.3 (21)
2.5.10.1.3 (21) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Kherson regional state administration
Implementation of the measure has not started
Not started
1.3 (20)
2.5.10.1.3 (20) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Kharkiv Regional State Administration
Implementation of the measure has not started
Not started
1.3 (19)
2.5.10.1.3 (19) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Ternopil Regional State Administration
Implementation of the measure has not started
Not started
1.3 (18)
2.5.10.1.3 (18) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Sumy regional state administration
There is progress in the implementation of the measure
In progress
1.3 (17)
2.5.10.1.3 (17) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Rivne Regional State Administration
Implementation of the measure has not started
Not started
1.3 (16)
2.5.10.1.3 (16) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Poltava Regional State Administration
Implementation of the measure has not started
Not started
1.3 (15)
2.5.10.1.3 (15) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Odesa Regional State Administration
Implementation of the measure has not started
Not started
1.3 (14)
2.5.10.1.3 (14) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Mykolaiv Regional State Administration
Implementation of the measure has not started
Not started
1.3 (13)
2.5.10.1.3 (13) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Lviv Regional State Administration
There is no progress in the implementation of the measure
In progress
1.3 (12)
2.5.10.1.3 (12) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Luhansk regional state administration
Implementation of the measure has not started
Not started
1.3 (11)
2.5.10.1.3 (11) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Kirovohrad Regional State Administration
Implementation of the measure has not started
Not started
1.3 (10)
2.5.10.1.3 (10) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Kyiv regional state administration
Implementation of the measure has not started
Not started
1.3 (9)
2.5.10.1.3 (9) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Ivano-Frankivsk Regional State Administration
There is progress in the implementation of the measure
In progress
1.3 (8)
2.5.10.1.3 (8) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Zaporizhzhia regional state administration
Implementation of the measure has not started
Not started
1.3 (7)
2.5.10.1.3 (7) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Transcarpathian regional state administration
There is no progress in the implementation of the measure
In progress
1.3 (6)
2.5.10.1.3 (6) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Zhytomyr Regional State Administration
Implementation of the measure has not started
Not started
1.3 (5)
2.5.10.1.3 (5) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Donetsk regional state administration
Implementation of the measure has not started
Not started
1.3 (4)
2.5.10.1.3 (4) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Dnipropetrovsk Regional State Administration
Implementation of the measure has not started
Not started
1.3 (3)
2.5.10.1.3 (3) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Volyn regional state administration
There is no progress in the implementation of the measure
In progress
1.3 (2)
2.5.10.1.3 (2) Performance by the National Agency for Rebuilding and Development of Infrastructure and regional state administrations all of the requirements of the order indicated in subclause 2.5.10.1.2, and ensuring the publication of open data on the Unified State Web Portal of Open Data in accordance with the list of data sets per CoST IDS (Infrastructure Data Standard), publication of data (particularly design documentation and methodology of calculation of the anticipated cost of procurement) in machine-readable format in accordance with the OC4IDS and OCDS standards
Vinnytsia Regional State Administration
There is no progress in the implementation of the measure
In progress